A takes 6 days less than B to do a work. If both A and B working together can do it in 4 days, how many days will B take to finish it ?
Let B alone take days to finish work 'W' then A alone takes
days to finish work 'W'.
Given : Both A and B finish the work in 4 days
B's one day work
A's one day work
A and B both one day work
Now,
(cancelling common W)
(Taking LCM)
(cross multiplication)
OR
because otherwise A's work will bw negative and will have no value.
Hence
B takes 12 days to complete work and A takes
days to complete the work.