Assertion (A): In the Event of violation of any legal right (tort) the aggrieved party is entitled to recover unliquidated damages.

 

Reason (R): The object of awarding damages to the aggrieved party is to put him in the same position in which he would have been if the wrong would not have been committed. Damages are therefore, assessed on that basis.

Option: 1

Both A and R are individually true and R is the correct explanation of A


Option: 2

Both A and R are individually true but R is not the correct explanation of A


Option: 3

A is true but R is false


Option: 4

A is false but R is true


Answers (1)

best_answer

In event of violation of some legal rights, damages can be awarded to the plaintiff. The object of awarding damages to the aggrieved party is to put him in the same position in which he would have been if the wrong would not have been committed. Hence the correct option is a. 