Which Section of Indian Contract Act, 1872, principally lays down the law governing liquidated damages.

Option: 1

Section 73


Option: 2

Section 24


Option: 3

Section 74


Option: 4

Section 70


Answers (1)

best_answer

Section 74 of Indian Contract Act, 1872, lays down the law governing liquidated damages. Hence correct option is c.