40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in ¾ of the time. Find the ratio of number of new men to number of old men.
12: 19
20: 27
27: 20
None of these
Men Days
40 28
=> 40 + x (¾) * 28 = 21
Men & days are inversely proportional
40 : 40+x :: 21 : 28
(40+x)21 = 28 * 40
=> 40 + x = (28*40)/21
x=(160/3)-40 = 40/3 = 13.3 = 13
New men = 40+13 = 53
Ratio 53/40 = 27/20