Provide Solution for RD Sharma Class 12 Chapter 29 Linear Programming Exercise 29.4 Question 38
Answer: 8 gold rings and 16 chains must be manufactured per day.
Hint:
Let, gold ring manufactured per day= x
Chains manufactured per day= y
Given:
Total number of rings and chain manufactured per day is almost 24.
Time taken to make a ring=1 hour
Time taken to make a chain=30 minutes
Maximum number of hours available per day=16 hrs
Profit on a chain =190 and profit on ring=300
Solution:
Let gold rings manufactured per day=x
Chain manufacture per day=y
LPP is:
Maximize Z= 300x + 190y
Subject to
Possible point for maximum Z is (16, 0), (8, 16) and (0, 24)
Hence Z MAXIMUM at (8, 16)
8 gold rings and 16 chains must be manufactured per day