Please Solve RD Sharma Class 12 Chapter 29 Linear Programming Exercise 29.4 Question 3 Maths Textbook Solution.
Answer:
A should work for 5 days and B should for 3 days.
Hint:
Let tailor A and B work for x and y days respectively.
Given:
Tailor A and B earn Rs15 and Rs20 respectively.
Solution:
Min
Since tailor A and B stitch 6 and 10 shirts respectively in a day. But it is desired to produce 60 shirts at least. So,
(First constraint)
Since tailor A and B stitch 4pants per day but it is desired to produce at least 32 pants so
(Second constraint)
Hence the required LPP .
Min
Subject to constraints
Since x and y not be less than zero.
The corresponding equation is
Point P(5,3) obtain by solving (i) and (ii)
Unbounded shaded region represents feasible region with corner points
Points |
|
Min z=135 at x=5 and y=3
Tailor A should work for 5 days and B should for 3 days.