Please Solve RD Sharma Class 12 Chapter 29 Linear Programming Exercise 29.4 Question 3 Maths Textbook Solution.

Answers (1)

Answer:

A should work for 5 days and B should for 3 days.

Hint:

Let tailor A and B work for x and y days respectively.

Given:

Tailor A and B earn Rs15 and Rs20 respectively.

Solution:

Min  z =15x+20y

Since tailor A and B stitch 6 and 10 shirts respectively in a day. But it is desired to produce 60 shirts at least. So,

6x+10y\geq 60

\Rightarrow 3x+5y\geq 30 (First constraint)

Since tailor A and B stitch 4pants per day but it is desired to produce at least 32 pants so

4x+4y\geq 32

\Rightarrow x+y\geq 8 (Second constraint)

Hence the required LPP .

Min z =15x+20y

Subject to constraints

3x+5y\geq 30

x+y\geq 8

x,y\geq 0 Since x and y not be less than zero.

The corresponding equation is

 

 

Point P(5,3) obtain by solving (i) and (ii)

Unbounded shaded region  A_{1}PB_{2}  represents feasible region with corner points  A_{1}(10,0), P(5,3), B_{2}(0,8)

Points

z=15x+20y

A_{1}(10,0)

150

P\left ( 5,3 \right )

135

B_{2}\left ( 0,8 \right )

160

Min z=135 at x=5 and y=3

Tailor A should work for 5 days and B should for 3 days.

 